1.
The Stipulated Price Contract Form
2.
The highest priority document int he contract documents, containing 8 articles.
3.
These conditions are pre-written in CCDC2 contracts
4.
If there is a discrepancy in the contract price between words and numbers, the ___ governs.
5.
These conditions are additional items we can add to a CCDC2 contract on top of the pre-written items and take precedence.
6.
The standard specification that describes what to use, how to use it, etc
7.
The standard specifications of how a product needs to perform when it's done
8.
If there is a discrepancy between the drawings and the specifications, we defer to the ______.
9.
The CCDC2 is a _____ price contract.
10.
A change ____ is an agreement to change the contract for an agreed amount or method of payment following a specific procedure.
11.
A change ____ authorizes the contractor to proceed with a particular change before a price is agreed.